Construction Progress
Construction Progress
4
multi-storey club-type building with 17 apartments of increased comfort
Earthworks and foundations – 100% (completed);
Monolithic frame – 100% (completed);
Walls and partitions – 100% (completed);
Internal engineering networks:
- water supply and sewage – 80% (work in progress);
- heating –10% (work started);
- electrical networks – 80% (work in progress);
- fire protection systems – 90% (work in progress);
- parking ventilation systems – 90% (installation work in the parking lot completed);
- low-voltage networks – 90% (work in progress)
Elevator – 95% (equipment installation completed);
Windows – 100% (completed);
Roof – 100% (completed);
Facades – 30% (work on the installation of wet facades on the roof has been completed, work is being carried out on the installation of facade thermal panels and on the installation of insulation of the facades of the 1st floor for facing with porcelain stoneware);
Finishing:
- Plastering of walls – 60% (work is being carried out on the 3rd floor);
- Fencing – 15% (work on the fences on the roof has been completed)
External engineering networks of water supply and sewage – 40% (work is being carried out)
Earthworks and foundations – 100% (completed);
Monolithic frame – 100% (completed);
Walls and partitions – 100% (completed);
Internal engineering networks:
- water supply and sewage – 70% (work in progress);
- heating –10% (work started);
- electrical networks – 70% (work in progress);
- fire protection systems – 80% (work in progress);
- parking ventilation systems – 90% (installation work in the parking lot completed);
- low-voltage networks – 90% (work in progress)
Filling of openings:
- windows – 100% (completed);
Elevator – 95% (equipment installation completed);
Roof – 100% (completed);
Facades – 20% (work on the installation of wet facades on the roof has been completed, work on the installation of facades with thermal panels and insulation of the facades of the 1st floor for facing with porcelain stoneware is being carried out);
Finishing:
- Plastering of walls – 50% (work is being carried out on the 3rd floor);
- Screed – 80% (work is being carried out);
- Fencing – 5% (work on the fence on the roof has been completed)